Project Timeline
Project Updates
Having completed all basic infrastructures, we now turn our attention to the development of the facilities included in our development plan. These include:
- Kiddies’ playground
- Clubhouse Building
- Nature Park & hiking trail
- Sportsfield
Efforts are been made to have these amenities install, or commence work as set out below.
- Kiddies Playground - Seventy five percent (75%) completed. Propose completion date September 2013.
- Clubhouse Building - Plans approved by Manchester Parish Council. Construction of building underway forty percent (40%) completed, proposed completion date June 2014.
- Nature Park & Hiking Trail – Construction underway work fifty percent (50%) completed. Projected completion date December 2013.
- Sportsfield - Ninety percent (90%) completed, proposed completion date September 2013.
Townhouse Development (The Glades)
- All major infrastructure works are now completed
- Verges landscaped, trees and shrubs planted.
- Work on the hard court is to commenced, completion is slated for September 2013
- The entrance columns are to be constructed in June 2013 and the electronic barrier will be installed by September 2013.